Work has now completed on Eastington's new community centre. Below, you will find images illustrating the progress of the project.January to March 2009
|
|
January. Upstairs internal work. |
January. Preparing for further solar panels. |
|
|
January. External cladding is started. | January. Preparing the front roof void for insulation. |
|
|
January. The front roof void complete. | January. Further internal progress. |
|
|
February. A touch of snow. | February. Tiling the front roof. |
|
|
February. Plasterboarding the roof. | March. Plastering starts. |
|
|
March. Ceilings complete first. | March. Electrician and plasterer in harmony! |
|
|
March. Solar panels and roof complete. | March. Close-up on the roof detail. |